Kenya launches Chinese-built fast train

China Daily Africa | Updated: 2017-05-28 08:23

The eagerly awaited inauguration of Kenya's modern railway infrastructure is set for May 31. The $3.8 billion Standard Gauge Railway, developed by China Road and Bridge Corp, has been completed six months ahead of schedule. It is expected to lower the cost of doing business in East Africa as it enables the transportation of freight from the port of Mombasa to Nairobi, with later connections to neighboring Uganda and Rwanda.

Here is a chronology of the milestones of the 472 km Nairobi-Mombasa route:

Phase I

Aug 12, 2009: CRBC signed MoU with Kenya Railways Corp.

2012: Submitted the preliminary design. Civil works contract and supply and installation of facilities, locomotives and rolling stock contracts signed.

Aug 19, 2013: President Xi Jinping and President Uhuru Kenyatta jointly witnessed the signing of the MoU on financing the Mombasa-Nairobi SGR Project.

May 11, 2014: Premier Li Keqiang witnessed the signing of the financing agreement with heads of state from East African countries.

Phase II

Dec 12, 2014: Project construction officially commenced.

Jan 23, 2015: Kenyatta visited the standard gauge railway observation segment of Section 3, and track-laying base of Section 6.

May 26, 2015 : Kenyatta visited the construction site of the Tsavo River Super Bridge.

Sept 19, 2015: Kenyatta and China Communications Construction Co President Chen Fenjian jointly attended the ground-breaking ceremony of the Nairobi Terminus.

Oct 30, 2015: Track-laying work commenced and operation planning and locomotive purchase started.

March 26, 2016: Zhang Dejiang, chairman of the Standing Committee of National People's Congress, went to Mombasa to see the Mombasa Terminus of Mombasa-Nairobi SGR Project.

Aug 10, 2016: Kenyatta met with Chinese Foreign Minister Wang Yi in Nairobi, showing willingness to actively promote the early completion and operation of the project and jointly build the East Africa Railway Network.

Late December 2016: The first locomotives were shipped.

Phase III

Beginning of 2017: Integration test and commission started.

June 1, 2017: Trial operation of SGR Project.

January 2018: Officially opened to traffic.

 Kenya launches Chinese-built fast train

Thousands of young men and women have had the chance to be part of the team behind the success of the Standard Gauge Railway Project.

?

?

 

Polar icebreaker Snow Dragon arrives in Antarctic
Xi's vision on shared future for humanity
Air Force units explore new airspace
Premier Li urges information integration to serve the public
Dialogue links global political parties
Editor's picks
Beijing limits signs attached to top of buildings across city
Copyright 1995 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
License for publishing multimedia online 0108263

Registration Number: 130349
FOLLOW US
主站蜘蛛池模板: 国产亚洲精品影达达兔 | 日韩综合久久 | 亚洲三级黄色片 | 国内精品一区二区2021在线 | 日本美女视频韩国视频网站免费 | 无毒在线 | 日韩欧美中文字幕一区二区三区 | 免费精品久久久视频 | 波多野吉衣 免费一区 | 99精品国产在热久久 | 久草在线新首页 | 久久久亚洲欧美综合 | 国产精品漂亮美女在线观看 | 香蕉久久一区二区不卡无毒影院 | 欧美xxxxx九色视频免费观看 | 久久伊人操| 91精品国产欧美一区二区 | 最新亚洲精品国自产在线 | 99在线观看视频 | aaaa毛片 | 成人性免费视频 | 色在线网站免费观看 | 日本免费人成黄页网观看视频 | 国产亚洲高清不卡在线观看 | 亚洲经典在线观看 | 九九视频在线观看视频 | 草草视频免费观看 | 特黄特色一级特色大片中文 | 日本毛片在线看 | 成年男人的天堂 | 亚洲成人视 | 怡红院日本一道日本久久 | 香蕉久久a毛片 | 亚洲香蕉一区二区三区在线观看 | 中国黄色网址大全 | 国内自拍区| 亚洲一区二区三区一品精 | 成人综合婷婷国产精品久久免费 | 特级一级毛片视频免费观看 | 日本a级毛片免费视频播放 日本a级三级三级三级久久 | 男人的天堂毛片 |